Energy costs of mining processes?
Generally, we think a 33% ore grade will likely require 100kWh of mining energy per ton of finished commodity, mostly consumed in the form of electricity, and emitting 50kg of CO2. Each $100/ton increase in global CO2 abatement costs will therefore increase the cost of mined commodities by c3%.